USNS Burlington (T-EFP 10) seen coming to Colombian Base Naval Logistica ARC “Bolivar” in Colombia, last month to prepare for the 20-nation UNITAS LXIV maritime workout. [U.S. Navy photo by Lt.j.g. Nicko West]
Boston Ship Repair, Boston, Mass., has actually been granted a $13,824,169 firm-fixed-price agreement for a 98-calendar day shipyard accessibility for a normal overhaul and drydocking of the Military Sealift Command expeditionary rapid transportation USNS Burlington (T-EPF 10).
Delivered by Austal U.S.A. in 2018, USNS Burlington is the the tenth Spearhead- course expeditionary rapid transportation run by the Military Sealift Command.
The Boston Ship Repair agreement consists of a base duration and 2 unexercised alternatives that, if worked out, would certainly bring its advancing worth to $13,880,012.
Work will certainly be executed in Boston, startNov 1, 2023, and is anticipated to be finished byFeb 6, 2024. Working resources funds (Navy) in the quantity of $13,824,169 are obliged for financial 2024, and will certainly end at the end of the .
Thie agreement was a local business set-aside with propositions obtained using the Government Point of Entry web site and 4 deals were obtained.
Military Sealift Command, Norfolk, Va., is the having task (N3220523C0190).
Located alongside the Black Falcon Cruise Terminal in Boston’s Seaport, Boston Ship Repair’s centers consist of a 65,000 loads variation graving dock with a size of 1,150 feet. It is among both participant shipyards of North Atlantic Ship Repair (the various other being Philadelphia Ship Repair).